Repairing the spire
There is an old letter in the presbytery which states work being done to the spire and tower as early as 1870, that is only 20 years after it was built.
Interview with Fr John Lavery about the roof project
September 2001
FJL: Many will have noticed the flaking plaster and peeling paintwork in certain areas inside the church. The damage was caused by rainwater entering the roofs of the sanctuary, nave and side chapels. Much of the problem was the result of slates coming loose from the roofs, which are in urgent need of repaiг.
Are the roofs that bad?
FJL: From a casual glance at the roofs on the left-hand side of the building, it seems that matters are not so severe. But on the side facing downhill towards the River, it is clear that patches of slates, as well as many single slates, have slipped out of place.
How did this happen?
FJL: The roofs were covered with Welsh slates when they were completed in 1849. They were attached with copper nails to horizontal wooden strips called battens. Copper was used since it did not corrode as fast as other common metals then available. However, even copper nails deteriorate over time, and in recent years the parish has had to have a score of slates replaced every twelve months or so. In 1999, many more slates started to come adrift, as the slating reached the end of its effective life, hence the rain entering the church.There was also a related problem, with some of the old rainwater hoppers and down pipes rusting away, allowing unseen water to build up in the valleys between the high roofs and side chapels. At the same time, some of the Kentish Ragstone in the walls had lost mortar, or had split, also letting water into our church. Nearing 150 years of age, the old place suddenly needed a thorough overhaul
Could we have done something in 1999?
FJL: We did! Once the scale of the problems became apparent, we applied to English Heritage for a grant to help pay for substantial repairs. Fortunately they had a Joint Scheme in operation at the time with the National Heritage section of the Lottery Fund, which made grants for emergency, high-level repairs in Grade II* listed buildings, in targeted areas of the country. Happily for us, Greenwich was one such area.
These grants could not be made for building works which had already started. After making a very detailed application, with the assistance of Watts and Partners, the firm of chartered surveyors in Blackheath, we were told in Autumn 2000 that we were to receive funding of £145,000, this being 60% of the estimated project cost (£241,000). The surveyors project management team then began producing detailed specifications of the necessary repairs, which had to be agreed with the architect at English Heritage.
Invitations to tender were sent out to four firms in June, and the contract was let to Messrs. Harry Neal Ltd in July. They will be the main contractor, using specialist sub-contractors for the scaffolding, stonework, etc. They began work on 28 August as parishioners have seen, with a target completion date in late November.